I am generating XML files exactly the same as saving out a sequence you create by hand. I reported this issue after release 2.9.5.
The scheduler will not move on past the first job when using the XML files with job priority set to ASAP.
This was only an issue after V 2.9.5. Never worked since.
You can manually create the sequence by hand, save it out to XML, then try to import it back, and it fails to run when set to ASAP priority.
The scheduler will not move on past the first job when using the XML files with job priority set to ASAP.
This was only an issue after V 2.9.5. Never worked since.
You can manually create the sequence by hand, save it out to XML, then try to import it back, and it fails to run when set to ASAP priority.